01342844118 [email protected]

Brunel University

Fire Door Replacement

CLIENT – Advanced Timber & Brunel University
VALUE – £108K
DURATION – 23 Weeks

Project Information:

To carry out the installation aspect of replacing and
certifying a total of 677 fire doors across 8 different
accommodation blocks.

This project was provided in 8 different stages with a
different accommodation complex to work in on
each phase, The complexes would typically contain
3-10 accommodation blocks. Works were carried out
around in live working facilities with students and
staff members.

 

PROJECT DESCRIPTION

The works included:-

Door replacement measuring survey.

Replacement of existing flat entrance door – sets

Replacement of existing bedroom door – sets

Replacement of existing kitchen door – sets 

Replacement of existing electrical distribution riser door – sets

Replacement of existing telecommunication riser door – sets

Replacement of existing plantroom door – sets

Door automation system fitted to specific doors

Access control system fitted to specific doors

Decorations completed to architraves and wall surrounds

All replacement door – sets were upgraded to FD30S & FD60S

BM Trada certification of installed fire doors

Installation of fire stopping measures

Upgrading of existing fire compartmentations

BM Trada certification of installed fire stopping measures

 

Head Office

Burstow Lodge Court, Chapel Road, Smallfield, Horley, Surrey, RH6 9YR

Call Us

01342844118

 

Email Us

[email protected]

 

Office Hours

Mon-Fri: 8am – 5pm
Sat-Sun: Closed

Pin It on Pinterest

Share This

By continuing to use the site, you agree to the cookie information. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close