Brunel University
Fire Door Replacement
CLIENT – Advanced Timber & Brunel University
VALUE – £108K
DURATION – 23 Weeks
Project Information:
To carry out the installation aspect of replacing and
certifying a total of 677 fire doors across 8 different
accommodation blocks.
This project was provided in 8 different stages with a
different accommodation complex to work in on
each phase, The complexes would typically contain
3-10 accommodation blocks. Works were carried out
around in live working facilities with students and
staff members.
PROJECT DESCRIPTION
The works included:-
Door replacement measuring survey.
Replacement of existing flat entrance door – sets
Replacement of existing bedroom door – sets
Replacement of existing kitchen door – sets
Replacement of existing electrical distribution riser door – sets
Replacement of existing telecommunication riser door – sets
Replacement of existing plantroom door – sets
Door automation system fitted to specific doors
Access control system fitted to specific doors
Decorations completed to architraves and wall surrounds
All replacement door – sets were upgraded to FD30S & FD60S
BM Trada certification of installed fire doors
Installation of fire stopping measures
Upgrading of existing fire compartmentations
BM Trada certification of installed fire stopping measures