Nuclear Medicine at St Helier Hospital

CLIENT – EPSOM AND ST HELIER TRUST

VALUE: Phase 1: £276,000 Phase 2&3: £232,000

DURATION – Phase 1: 10 weeks Phase 2&3: 5 weeks

The adaptation and refurbishment of the Nuclear Medicine Department at St Helier Hospital was split into 3 phases – All phases were carried out around patients. This department uses small amounts of radioactive material to image both organ function and structure. Areas refurbished: Scanning Room, Control Room, Reporting Room, WC’s, Staff Kitchenette, Reception, Cold Waiting Area, Hot Waiting Area, Corridors, Lobby, Cardiac Stress Room, Prep/Injection Room and Laboratory.

The works involved:
-Demolition
-New partitions
-Code 4 Lead lining of new surrounding areas
-Electrical
-Mechanical (new ventilation, AC installation, pipework reconfiguration and new sanitary ware).
-New Acrovyn doorsets
-Installation of new lead-lined laboratory
-Installation of lead-lined pass through hatches
-Decorations
-Flooring
-Suspended ceilings
-LED skylight panels in Scanning Room